Skip to content

Hydroseeding to start at EWEB East 40th site this Friday

Dear East 40th Neighbors,

On Friday, Nov. 19 crews will HydroSeed the excavated slopes as a way to stabilize the exposed soils.

HydroSeeding is a process where seed, mulch, fertilizer, soil amendments, and water are combined to form a slurry that is sprayed onto the ground to establish vegetation and control erosion.

Following is the current blasting schedule for the next couple of weeks:

  • Thursday, Nov. 18
  • Tuesday, Nov. 23
  • Wednesday, Nov. 24 (make up for Thanksgiving)

As a reminder, scheduled blasts will occur between 1-1:30 p.m. The actual blast will last only a couple of seconds.

Horn safety signals will sound 5 minutes and 1 minute before the blast and at the conclusion of the blast.

If you are near the construction site and hear a horn signal, please be aware blasting activity will occur shortly and follow instructions of site personnel or any additional signage that may be posted.

Additional updates

Contact us with questions

If you have questions or input, please don’t hesitate to reach out to the project team at 541-685-7899 or water.storage@eweb.org. Emails sent to this address will reach:

  • Laura Farthing, Project Manager/Senior Civil Engineer
  • Jen Connors, Communications Supervisor
  • Jeannine Parisi, Customer Relationship Manager
  • Wally McCullough, Water Engineering Supervisor
Back To Top